Recently, Duong Nhat completed a nearly 600 m³ base slab concrete pour at the Centralized Effluent Treatment Plant of Prodezi Long An Industrial Park, Phase 1, with a treatment capacity of 4,000 CMD. The project is developed by Prodezi Long An Joint Stock Company, with Duong Nhat acting as the EPC General Contractor. This is an essential environmental infrastructure of the new-generation Prodezi Eco-Industrial Park in Long An.
The completed base slab concrete pour constituted a critical milestone for the project. Specifically, site construction faced numerous challenges: unavailability of access road, lack of construction power supply and water source for construction, along with rainy-season weather in the South, narrow working space, restricted truck movement, and limited site access.
All concrete pouring activities were continuously organized and maintained for 8 hours, with two concrete pumps operating in parallel, supported by teams of engineers, workers, and standby crews working in shifts, ensuring adherence to all standards of progress, quality, and absolute safety.
Through robust collaboration between Duong Nhat’s Site Management Board, the Supervision Consultant, and the Investor, the concrete pour was completed on schedule, adhering to all quality, aesthetics, and safety requirements despite unfavorable weather and strict technical demands
Duong Nhat wishes to express sincere gratitude to the Investor, the Supervision Consultant, and all project Partners for their contribution to the success of this critical milestone.