With the purpose of environment protection and sustainable development, Phuoc Hoa Kampong Thom Rubber Development Co., Ltd assigned Duong Nhat as the general contractor for the Project “ Implementing the wastewater treatment plant for Phuoc Hoa Kampong Thom rubber latex processing factory” located in Cambodia.
Recently, the Project has just been finished the construction item and moved to the stage of ME, Electrical installation and Commissioning.
In spite of difficult execution conditions that construction location is far from the residential area, transportation and freight are inconvenient, the construction item was finished within 125 execution days, which was ahead of schedule thanks t othe effort of the Executive Board.
“Duong Nhat Team” has constantly tried to make the project complied with schedule, quality and aesthetic as committed to the Investor.
Congratulations on “Duong Nhat Team”.
DUONG NHAT – “ALWAYS CARRY OUT BETTER THAN COMMITMENT”