Commencement ceremony of project: Wastewater treatment system for Suoi Ke extension rubber processing factory, phase 2nd – Binh Thuan

(Duong Nhat) On the morning of June 11th, 2014 at Suoi Ke Rubber processing factory, Binh Thuan Rubber One Member Co., Ltd in coordination with DUONG NHAT hosted a commencement ceremony of Turnkey project “Wastewater treatment system of project Extension of Suoi Ke Rubber processing plant, phase 2nd with capacity of 850 m3/day – Binh Thuan Rubber One Member Co., Ltd”. Treated wastewater will reach Standard QCVN 01:2008/BTNMT and QCVN 40:2011/BTNMT column A.

 

Suoi Ke

 

The scope of works in construction contract included: Technical design, design of construction work, equipment supply and installation, operation, commission and handover. This project be implemented with working period of 420 days under Turnkey form.

 

DUONG NHAT – “ALWAYS CARRY OUT BETTER THAN COMMITMENT”